See the home get built!
USE YOUR BACK
BUTTON
(or Alt + the Left Arrow)
after clicking on photos
to return to this page.
To be done:
Minor Stuff
April 2nd:
(Cement, Stucco Ledges)
April 1st:
(Grading, Shower Seat, Cement Layout)
March 30th:
(Appliances Installed)
March 29th:
(Driveway, Garage Doors, Shower Doors)
March 26th:
(Raingutters)
March 25th:
(Alarm, Grading, Driveway)
March 24th:
(Mbr Closet, Mirrors)
March 23rd:
(Flooring)
March 22nd:
(Exterior Lights, Grading)
March 20th:
(Stucco Finish Coat)
March 19th:
(Laminate Flooring)
March 18:
(Electrical/Plumbing, Lights & Fixtures)
March 17:
(Countertops)
March 16:
(Vinyl, Cabinets, Cultured Marble)
March 15:
(Stucco Base, Sub Floors, Tile Entry)
March 12th:
(Final Paint)
March 11th:
(Doors & Trim)
March 10th:
(Primer)
March 9th:
(Painting, Stucco Prep)
March 3-6th, March 8th:
(Finish Mud & Tape, Basement Windows in,
Final Electrical, Hang Doors, Trim, Shelves, etc.)
February 19th-March 2nd:
(Finish Plumbing, Gas, Electrical & Roof
Insulate, Soffit, Inspections, Sheetrock, Mud & Tape)
February 18th:
(Roof, Plumbing, Electrical)
February 17th:
(Roof Decking)
February 16th:
(Roof Decking, Heating Ducts, Interior Gas)
February 14th:
(Nothing?)
February 13th:
(Roof Trusses)
February 12th:
(Interior Framing)
February 11th:
(Garage Walls)
February 10th:
(Gas Line)
February 9th:
(Framing)
February 7th:
(Floor)
February 6th:
(Basement Framing, Stairs, Floor Joists)
February 5th:
(Top-plate & Measuring)
February 4th:
(Snow)
\February 3rd:
(Snow)
February 2:
(Garage Slab)
January 31st:
(Wood was delivered. Nothing else...)
January 30th:
(Basement Floor & Ben's Office Slab)
January 28th & 29th:
Oops! I forgot to take the camera...
Well, Actually, I had the camera, but no memory stick.
Window wells, underground plumbing installed...
Back-filled dirt around foundation and in garage.
January 27th:
(Begin underground plumbing)
January 26th:
(Foundation Walls)
January 23rd:
(Footings)
January 22nd:
(The REAL digging begins)
January 21st:
(Groundbreaking)